unrated
procurement
90% conf.There was confusion about the contract start and end dates, with the contract start being 1 March and prior contract showing end as 1 February, but the actual end date was 28 February following a court ruling and service level agreement (SLA).
“because of the confusion of dates of the contract starts on 1 March and the previous contract was stated that it ended on 1 February. Whereas if a contract starts on 1 March, it actually ends on 8 February because it is valid for a fully year... But eventually it was cleared out that because of the court ruling and the SLA, it commenced 1 March and therefore ends on 28 February”